87% COMPLETION OF DAVAO BYPASS ROAD TUNNEL
It's 87.72% ( 1,965 meters ) completion progress as of October 2024 for Northbound side and for Southbound side, it's 78.30% ( 1,761 meters ) progress.
FYI: The entire Davao City Bypass Construction Project has 45.62 km. from Barangay Sirawan, Toril, Davao City to Brgy. J.P. Laurel, Panabo City, Metro Davao.